Bridge Load Testing - ROB, Bandikui

Client: PWD Rajasthan, Division SikandraLocation: Bandikui, Dausa, RajasthanTimeline: 2025
Bridges
Bridge Load Testing - ROB, Bandikui
Executive Summary

Load testing of a 30 m span PSC box girder bridge as per IRC SP:51-2015, including instrumentation, staged loading, deflection monitoring and structural performance evaluation.

Project Highlights

  • 30 m span PSC box girder bridge
  • 100-tonne test load using four 25-tonne vehicles
  • Seven dial gauges installed at different locations
  • Maximum permissible deflection of 34.5 mm
  • Measured deflection within permissible limit

Scope of Work

  • Staged loading and instrumentation
  • Deflection monitoring at each load stage
  • Crack-width measurement using crack-gauge microscope
  • Evaluation of readings as per IRC SP:51

Engineering Methodology

STAGE 1

Instrumentation Setup

STAGE 2

Staged Loading

STAGE 3

Deflection and Crack Monitoring

STAGE 4

Evaluation and Report

Standards & Codes Applied

IRC SP:51-2015Load testing of bridges

Certified Deliverables

  • Load test report and test results
  • Deflection readings at each load stage
  • Crack-width observations
  • Structural performance evaluation
  • Conclusion on safe load-carrying behaviour

Project Outcome & Impact

Under the full 100-tonne test load, measured deflection remained within the permissible 34.5 mm limit, confirming satisfactory structural performance.

PROJECT ENGAGEMENT

HAVE AN ENGINEERING CHALLENGE?

Tell us about your project, site condition, testing requirement or engineering challenge. Our team can help identify the appropriate investigation, testing or engineering approach.

Direct Hotline
+91 81144 28016
Engineering Desk
info@namotech.in
Testing Accreditation
NABL Cert. TC-7290